Wire Cutting Machine ROI Analysis: How Long to Pay Back?

Cost Analysis · 2026

Before buying equipment, the key question is: how long until payback? Here is a real-case calculation.

1. Investment Cost (One-Time)

ItemAmount (CNY)Note
Machine (S-02)48,000Medium servo model
Spare blades2,0002 tungsten blade sets
Freight1,500Domestic logistics
Installation0Free on-site by Surui
Training0Free
Total51,500

2. Operating Cost (Per Year)

ItemAnnual (CNY)Note
Electricity3,6004kW × 8h × 300d × 0.38/kWh (30% load)
Blade consumables3,000~1 set per quarter
Maintenance1,000Lubricants, wear parts
Labor (0.5 person)30,0001 operator for 2 machines
Total37,600

3. Benefit Comparison (Key)

Option A: Manual Cutting (Current)

ItemValue
Workers2
Monthly wage eachCNY 5,500
Annual labor costCNY 132,000
Daily output~15,000 pcs (2 workers)
Defect rate3% (~450 pcs/day)

Option B: Machine Cutting (S-02)

ItemValue
Workers0.5 (part-time monitoring)
Annual costCNY 37,600 (all-in)
Daily output~60,000 pcs (400/min × 8h × 30%)
Defect rate0.5%

4. Payback Calculation

Annual Savings

Labor savings = 132,000 − 37,600 = CNY 94,400/year

Output increase = 60,000 / 15,000 = 4×

Defect reduction = 3% → 0.5%, saving ~CNY 8,000/year

Total annual benefit = 94,400 + 8,000 = CNY 102,400/year

Payback Period

Investment / Annual benefit = 51,500 / 102,400 = ~6 months

★ i.e. payback in half a year, then ~CNY 100,000 net per year

5. Three-Year Total

ItemManualMachineDifference
3-year total cost396,000164,300Save 231,700
3-year output13.5M pcs54M pcs+40.5M pcs
Quality (defect rate)3%0.5%6× better
ManagementHard to hire, high turnover1 person / 2 machinesMuch easier

6. Beyond Money

  • Hiring is no longer a problem: no reliance on skilled workers; new staff productive in 1 day
  • Consistent quality: ±0.03mm regardless of operator condition
  • Predictable delivery: confident to take large orders
  • Access to high-end orders: precision qualifies you for precision part contracts
  • The machine is an asset: 10-year life with residual value

7. Recommendations by Volume

Daily NeedModelInvestmentPayback
< 30k pcsM-04~30k6-9 months
30k-100k pcsS-02~50k5-7 months
100k-300k pcsD-01 / D-0270-80k6-10 months
> 300k pcs / multi-varietySR12~100k8-12 months

Want a calculation for your factory?

Tell us: current output, headcount, wage level, product requirements → free ROI report.

Free Assessment
Common Wire Cutting Machine Faults: 10 Problems and Solutions
Troubleshooting · 2026